Grid Connection of Generating Facilities
Applicant | Generation Facility Connected | Required capacity for the grid connection of generating units for power supply to the grid, voltage rating | The grid connection agreement date, price (excl. VAT) | Status of the grid connection of the facility at the end of 2020 |
---|---|---|---|---|
Rosneft | Tuapse Refinery | 24 MW, 110 kV | 01.04.2010 RUB 56.37 mln | The agreement is on the way. On December 21, 2016, Rosseti Kuban notified the Applicant of the completion of work provided for by technical specifications and the readiness to the actual connection of the Facility according to the applicable legislation. The grid connection deadline is May 30, 2022 |
ART-TECH LLC | Electric facilities of a land plot for the arrangement of a logistics center | 6.2 MW, 10 kV | 29.05.2020, RUB 4.14 mln | The agreement is on the way. The grid connection deadline is May 29, 2022 |
Renewable energy sources LLC | Electric facilities of a land plot for space activities, defense, security | 4.5 MW, 10 kV | 12.08.2020, RUB 7.13 mln | The agreement is on the way. The grid connection deadline is August 12, 2022 |
Verkhnebakansky Cement Plant OJSC | Verkhnebakansky Cement Plant OJSC’s power plant | 56.41 MW,6 kV | 03.09.2015 RUB 0.09 mln | The agreement is on the way. On February 18, 2019, Rosseti Kuban notified the Applicant of the readiness to the actual connection of the Facility according to the applicable legislation. The grid connection deadline is December 31, 2021 |
Novoroscement OJSC | GPU-based (gas piston unit) energy center with a capacity of 17,600 kW | 17.60 MW 110 kV | 04.03.2019 RUB 11.40 mln | The agreement is on the way. On March 4, 2019, Rosseti Kuban notified the Applicant of the readiness to the actual connection of the Facility according to the applicable legislation. The grid connection deadline is March 4, 2021. In accordance with the Applicant’s request to extend the grid conenction deadline, a corresponding supplementary agreement to the contract is being prepared |
LUKOIL-Ecoenergo LLC | Power generating devices of a small HPP | 1.5 MW,6 kV | 01.12.2020, RUB 13.18 mln | The agreement is on the way. The grid connection deadline is December 1, 2022. |
Energo-Volt LLC | GPU-based energy center with a capacity of 24.8 MW | 3.89 MW,6 kV | 17.09.2018, RUB 16.9 mln | The agreement is on the way. The grid connection deadline is September 17, 2022. |
KNAUF GIPS KUBAN LLC | GPU-based energy center with a capacity of 4 MW | 4 MW,10 kV | 10.12.2018, RUB 2.48 mln | The agreement is on the way. The grid connection deadline is December 10, 2022. |
EuroSibEnergo-Kuban LLC | Power generating devices of a land plot. The residential area for IV hazard class enterprises of various types (construction of mini-TPPs) | 4.44 MW, 10 kV | 22.05.2018, RUB 2.75 mln | The agreement is on the way. The grid connection deadline is May 22, 2022 |
Cheeses of Kuban LLC | GPU-based energy center with a capacity of 3,896 kW | 3.89 MW, 6 kV | 01.07.2019, RUB 2.52 mln | The grid connection deadline is July 1, 2021. The agreement execution date is October 15, 2020 |
Renewable energy sources LLC | Power generating devices of a land plot for the arrangement of a production enterprise | 4 MW, 10 kV | 25.02.2020, RUB 8.31 mln | The grid connection deadline is February 25, 2022. The agreement execution date is September 1, 2020 |